Sabita is an industry organisation that promotes the
development and application of bituminous materials. It is registered as
an organisation not for gain and supports its members (consulting
engineers, suppliers and contractors) through research, education,
engagement with client bodies and promotion of sustainable practices.
Under scrutiny is a matter that was initiated around 2001 with the
intent to bring about a transparent mechanism that would deal with the
rise and fall of the bitumen component in asphalt costs.
As road building contracts could span lengthy periods, a mechanism was
sought to minimise uncertainty of input costs, resulting largely from
externalities such as crude costs and exchange rate fluctuations.
Due to various parties not being able to reach agreement, this however
was never implemented as intended. The intent of this initiative was to
bring about a transparent mechanism between contractors and client
bodies that would deal with input cost fluctuations and never to flout
competition law.
Saied Solomons, CEO
5/3/2010
It is envisaged that the above report and its appendixes
will form the basic framework for a new guideline on Warm Mix Asphalt (WMA)
in South Africa.
The WMA Interest Group will keep you informed of all
future developments.
... Latest News
Download GAPA statement
here.
2 March 2010
Creamer Media
The South African National Roads Agency Limited (Sanral) has
raised a further R837-million under its Domestic Medium Term
Note Programme in the second auction for this year, bringing
the total funds raised for its road upgrade projects to
R15,9-billion.
The agency again tapped into its two bonds with maturities
in 2020 and 2034, as well as issued a new 2023
inflation-linked bond, for this auction, for which it
received overall bids totalling R1,1-billion. Sanral has, to
date, raised R9,95-billion without guarantee, and a further
R5,95-billion under guarantee from the South African
government.
The funds were being used to fund the expansion and upgrade
of toll roads, particularly its R20-billion Gauteng Freeway
Improvement Project (GFIP), which was planned to be
substantially completed before the 2010 FIFA World Cup.
In February, Sanral GFIP project manager Alex van Niekerk
reported that the first phase of the project was, on
average, about 70% completed.
March 2, 2010
Donwald Pressly, Business Report
The national roads system is top notch and repairs can be
swiftly made, according to Transport Minister S'bu Ndebele,
but the provincial and municipal road maintenance programme
is severely wanting.
To overcome this, road allocations from the fiscus could be
"ring-fenced" to ensure the funds "for tar" were spent,
Ndebele said yesterday. At a parliamentary briefing on the
government's infrastructure programme, Ndebele said there
was "no maintenance backlog on the national network".
However, he said "we need to move towards a provincial
emphasis where we replicate the systems that at national
level" allow for world class maintenance and repairs. The SA
National Roads Agency Limited (Sanral) is responsible for 16
000km of national roads, including 3 000km of toll roads.
Ndebele noted that nationally there was a system in place to
repair potholes in 48 hours.
He acknowledged that other roads received annual funding of
between R8 billion and R9bn, whereas an estimated R13bn a
year was needed over the next five years to avoid
underfunding. On resolutions to the underfunding problem,
running at about R5bn a year, Deputy Transport Minister
Jeremy Cronin said applying the Sanral example at provincial
and municipal level was instructive, but he noted problems
of corruption at a similar agency formed in Limpopo. "There
are some challenges in that provincial road agency," he
said, noting that the roads agency contracted the road works
to private companies but it had to keep a tight rein on
monitoring the work. He noted that Sanral would soon take
charge of another 4 000km of the road network, some of which
was now the responsibility of the provinces.
He said road funding would shift away from the metropolitan
cities hosting World Cup events to other roads in future.
"Spending will shift to smaller towns and rural areas and
hopefully we will get a little bit more out of the
Treasury," said Cronin.
Linda Ensor, 2 March 2010
Business Day
The Department of Transport is in talks with the Treasury
about the possibility of setting aside dedicated funds to
address backlogs in the construction of national, provincial
and municipal roads. The backlog of funding road
infrastructure amounts to about R64bn, and the transport
department hopes that more funds will be made available for
infrastructure development in smaller towns once
preparations for the Soccer World Cup have been completed.
The money will be made available through the use of grants
which have been used successfully for the development of the
bus rapid transport system. "Even though this year we are
investing R18bn on roads (nationally) and R23bn on the
Gauteng freeway improvement scheme, this is not enough,"
Transport Minister Sibusiso Ndebele told a ministerial
cluster briefing in Parliament yesterday.
From 2001 to 2008 aggregate expenditure on roads grew from
R8,2bn to R9,2bn but the investment required was calculated
to be R64bn over five years starting with the 2003-04
medium-term expenditure framework. "This means that we have
been underfunding our own requirements and projections,"
Ndebele said. Over the next three years R70bn had been
earmarked for road development and upgrades. "We are
gathering information on the extent, condition and
investment requirements of all roads authorities in the
country so that a composite picture can be drawn and
effective plans and strategies implemented." Ndebele was
briefing the media on the transport-related aspects of the
government's R846bn infrastructure programme.
He noted that in the next five years Transnet would invest
about R93,4bn in ports, rail and pipelines infrastructure
and operations to improve efficiencies. In the last five
years to 2009 -10 it had invested R75,3bn. Ndebele was also
questioned about collapsing bridges in Limpopo, allegedly
built by a company partly owned by African National Congress
Youth League president Julius Malema. He said the matter was
serious, and his department would investigate.
2010-02-24
www.news24.com
About R5.5bn has been committed towards the construction and
upgrading of roads in Gauteng, the provincial department of
roads and transport said on Wednesday. MEC Bheki Nkosi said
in a statement that his department had entered into a
partnership with its private sector partners, in which the
money was committed to road works over the next five years.
"This plan will yield the construction and maintenance of 1
500km of provincial roads," he said. By the end of this
financial year, the department would have upgraded 80km of
roads in Sharpeville, Refiloe, Mamelodi, Atteridgeville,
Kagiso, Katlehong, Mohlakeng and Orlando.
The roads in these areas had been upgraded from gravel to
tar, with the installation of storm water drainage systems.
Nkosi said the department will also construct pavements on
high volume pedestrian roads within the 20 prioritised
townships. New number plates The department also intended
ensuring that at least 200 000 vehicles had the new
aluminium number plates with security features by the end of
October 2010. This would partly involve a roll call of all
vehicles in Gauteng to ensure that they were properly
registered and licensed. Nkosi said plans to root out
corruption in driver's license testing centres were also
underway with the installation of high-tech testing systems
across Gauteng to reduce the dominance of human factors in
test outcomes.
The department also planned to expand its centres for
service delivery by entering into service level agreements
with the South African post office on driver's license
renewal sites. Roads ready by April 2010 Meanwhile, Nkosi
said the key strategic road network for smooth travel during
the 2010 Fifa World Cup would be ready by the end of April.
These roads included the K29 Malibongwe Drive upgrade, which
links Lanseria Airport with Johannesburg and Pretoria.
The upgrading of the Albertina Sisulu highway, which is a
crucial gateway into the province from OR Tambo
International Airport, would also be completed by the end of
April 2010. Nkosi said the department would complete the
beautification of this route at the same time as the
upgrading. He also mentioned that the Gautrain project's
phase one, which is the link between Sandton and the OR
Tambo International Airport, was expected to be completed by
June 2010. "This presentation becomes our 2010/11 service
delivery map for each of the programmes highlighted by the
premier during her state of the province address on Monday,"
Nkosi said.
Business Report
1/3/2010
The slow destruction of South Africa's roads network by
heavily-laden trucks came under the spotlight at Parliament
on Monday.
"A key problem on our roads is the massive migration of
freight, very heavy freight, onto the road system. That's
freight that should be on the rail system," Deputy Transport
Minister Jeremy Cronin told journalists at an infrastructure
development cluster media briefing. Cronin said his
department was working closely with public enterprises on
the matter. "Because we've really got to improve, very
significantly, the Transnet freight rail system... We need
to get much, much, much more freight back onto rail. It's
the main cause... for damage to our road systems," he said.
According to a briefing document distributed to journalists,
the rail freight system is "fraught with serious performance
challenges". It says the single-most important cause of
these is "historical under-investment in infrastructure,
rolling stock and operating equipment". As a result, the
system was unable to meet current freight demand. Transnet
had embarked on "massive" infrastructure and operational
investments to improve service levels. "Transnet will in the
next five years invest about R93.4 billion into ports, rail
and pipelines infrastructure and operations to improve
efficiencies in these areas of the freight logistics
sector," the document states. Over the past five years --
between 2005/06 and 2009/10 -- it had sunk R75.3 billion
into these areas.
Cronin said maintenance of South Africa's
roads network posed a "major challenge", but the problem did
not lie with the country's SA National Roads Agency-managed
national roads. "The problems tend to occur at a provincial
and municipal level," he said.
There were several reasons for this, including under-funding
to the tune of about R60 billion. "That's steep, and as you
fall back from one year to another, the condition of the
roads gets worse and they deteriorate quite rapidly." Cronin
said that after the 2010 Soccer World Cup, the focus would
shift from roads infrastructure in the host cities, towards
those in small towns and rural areas. "Hopefully we can
begin delivering some of the spend in that direction, and...
we can get a little bit more out of Treasury," he said.
According to the briefing document, South Africa's
"estimated total proclaimed road network" stretches 535
000km.
The document also acknowledges that the R18 billion
earmarked for spending on roads this year -- not including
the R23 billion to be spent on the Gauteng Freeway
Improvement scheme -- is "not enough". Meanwhile, tyre
manufacturer Continental on Monday warned motorists to
beware of potholes. "The weather over recent months has
caused potholes of all sizes on many roads, including
motorways, so motorists need to take extra care when driving
to avoid damage to their own car," it said in a statement.
Road repairs were not likely to be made soon. "Local
councils will probably not be able to carry out all the road
repairs straight away -- so motorists might need to get used
to the idea of living with potholes for a while," it said. -
Sapa
2010-02-24
www.news24.com
About R5.5bn has been committed towards the construction and
upgrading of roads in Gauteng, the provincial department of
roads and transport said on Wednesday. MEC Bheki Nkosi said
in a statement that his department had entered into a
partnership with its private sector partners, in which the
money was committed to road works over the next five years.
"This plan will yield the construction and maintenance of 1
500km of provincial roads," he said. By the end of this
financial year, the department would have upgraded 80km of
roads in Sharpeville, Refiloe, Mamelodi, Atteridgeville,
Kagiso, Katlehong, Mohlakeng and Orlando.
The roads in these areas had been upgraded from gravel to
tar, with the installation of storm water drainage systems.
Nkosi said the department will also construct pavements on
high volume pedestrian roads within the 20 prioritised
townships. New number plates The department also intended
ensuring that at least 200 000 vehicles had the new
aluminium number plates with security features by the end of
October 2010. This would partly involve a roll call of all
vehicles in Gauteng to ensure that they were properly
registered and licensed. Nkosi said plans to root out
corruption in driver's license testing centres were also
underway with the installation of high-tech testing systems
across Gauteng to reduce the dominance of human factors in
test outcomes.
The department also planned to expand its centres for
service delivery by entering into service level agreements
with the South African post office on driver's license
renewal sites. Roads ready by April 2010 Meanwhile, Nkosi
said the key strategic road network for smooth travel during
the 2010 Fifa World Cup would be ready by the end of April.
These roads included the K29 Malibongwe Drive upgrade, which
links Lanseria Airport with Johannesburg and Pretoria.
The upgrading of the Albertina Sisulu highway, which is a
crucial gateway into the province from OR Tambo
International Airport, would also be completed by the end of
April 2010. Nkosi said the department would complete the
beautification of this route at the same time as the
upgrading. He also mentioned that the Gautrain project's
phase one, which is the link between Sandton and the OR
Tambo International Airport, was expected to be completed by
June 2010. "This presentation becomes our 2010/11 service
delivery map for each of the programmes highlighted by the
premier during her state of the province address on Monday,"
Nkosi said.
Stuart Farrow, Democratic Alliance
21 February 2010
Deterioration of R50 demonstrates need for road
maintenance overhaul
A major cause of the potholes that riddle South African roads
is overloading and the transportation of freight on roads, instead
of the utilisation of the rail network. A study by the CSIR
Transportek revealed that the annual damage to the network of
provincial and national roads caused by overloading was estimated
in the mid 1990s to be R450-millon per annum. At today's prices,
this figure would be between R700 and R800-million per annum.
A salient case in point is the deterioration of the R50 provincial
road between Leandra and Standerton in Mpumalanga - an area
where a Sasol Petrochemical plant is located as well as numerous
coal mines.
Photographs sent to the DA of the R50 road reveal that is in
a state of advanced decline. The road is riddled with potholes
that have occurred as a result of a substantial period of neglect.
This road is used for the transportation of coal between coal
mines and a Sasol petrochemical plant. The transportation of
these bulk goods has undoubtedly accelerated the rate of deterioration.
However, had restrictions been put in place to limit the weight
of goods these trucks can transport, been put in place, and
maintenance been carried out timeously, this road would almost
certainly not have deteriorated to the current dire state it
is in.
The solution to overloading and the ancillary damage to the
road network is twofold - the creation of a dedicated road maintenance
fund and the imposition of strict restrictions on the maximum
permitted axle weight and length of heavy vehicles be reduced
to meet international norms.
It is a matter of concern that between 1988 and 1999, the percentage
of the road network in good or very good condition fell from
75% to 33%. A more recent report emanating from the AA in November
2008 indicates that about 60% of national or provincial roads
are in poor or very poor condition compared to 22% in 1998.
Not only has the ANC-led government neglected to ensure that
South African roads are adequately maintained, but the costs
of effecting such repairs has also been allowed to rise exponentially.
The typical cost of maintaining a road, when maintenance is
done timeously, is R100 000 per kilometre. If the road is left
for three years, the costs rise to R600 000, and if the road
is left for a further five years, it will rise to R1.8-million
per kilometre.
The cause of this deterioration is neglect and poor planning
by the national and provincial governments in allocating funds
from budgets for road maintenance. For example, the City of
Johannesburg utilised only 2% of its operational expenditure
on repairing and maintaining the city's roads over the last
5 years.
The move by the Minister of Finance to increase government's
spending on transport projects to nearly R30-billion over the
next three years is one to be welcomed. However, it is still
a matter of concern that the Minister made no mention of a fund
specifically dedicated to the maintenance of South Africa's
road infrastructure. The DA has repeatedly called for the establishment
of a dedicated road maintenance fund to be sourced from the
fuel levy, public-private partnerships and state-guaranteed
money-market loans.
Furthermore, in order to encourage a move of the transportation
of goods from roads to railways, the DA will be writing to the
Minister of Transport proposing that:
.
The maximum permitted axle weight and length of vehicles be
reduced in conjunction with international norms
. More weighbridges
be allocated to local municipalities and provinces A punitive
tax be imposed on freight en-route where rail services exist
. Heavier punishment for habitual overloading offenders
. The introduction
of legislation that certain hazardous and bulk goods should
go by rail as opposed to road.
Irma Venter
19th February 2010
Engineering News
On average, phase one of the Gauteng Freeway Improvement
Project (GFIP) is around 70% completed, says South African National
Roads Agency Limited (Sanral) GFIP project manager Alex van
Niekerk.
However, he adds that this is a general figure, with some early-starter
projects further advanced, and those which broke ground only
recently below this mark. Also, one can measure a project's
advance by the money you have spent or the time that has elapsed,
but as we are doing some high-cost finishing work only at the
end of some contracts, these two aspects are not necessarily
in sync. The R15,1-billion first phase of the GFIP aims to
upgrade 185 km of freeway network in Gauteng, through, for example,
improved lighting, upgraded interchanges, and the widening of
freeways through the addition of new lanes. Construction
started in 2008.
The R21 and the World Cup
The abnormally high rainfall seen in January has definitely
had an impact on the project's progress, says Van Niekerk.
Some of the work sites had 440 mm of rain, and days where the
contractors could not work at all. Van Niekerk says Sanral
will do an assessment later this month to determine whether
GFIP first phase work is running according to schedule. The
full first phase, the open-road tolling system included, is
to be operational in 2011. In December, things looked good,
but this may now have changed, he adds. He says Sanral will
use the assessment to determine whether the agency and the various
contractors active on the project should make special arrangements
to complete certain projects in time for the 2010 FIFA World
Cup.
The R21 airport road and the N1 between Soweto and the 14th
Avenue exit, near Soccer City, are two projects which have to
be completed in time for the June kick-off, as well as certain
new lane additions to other stretches of freeway, and work on
some of the interchanges. For now, Van Niekerk says the assessment
is that the R21 will be open for traffic in time for the World
Cup, but that some final touch-ups will remain to be done in
the south-bound lanes following the sports event. But the public
won't even notice anything amiss, he adds. The R21 is being
upgraded from a four-lane freeway to an eight-lane freeway.
The N1 also currently remains on schedule for completion before
the World Cup. Further phases of the GFIP will include 223 km
of upgrades, and new roads of 158 km. The final GFIP scheme
will encompass 561 km.
Lindsey Berry
19 February 2010
Engineering News
Africa has been pegged as one of the key hubs for development
in the future and the availability of engineering skills will
be critical in the implementation of much-needed new infrastructure
on the continent.
South Africa, in particular, is experiencing a period of booming
infrastructure develop- ment with projects such as State-owned
power utility Eskoms new power stations, the soccer stadiums
for the FIFA World Cup, the Gauteng Freeway Improvement Project
and public transport infrastructure development, such as the
Gautrain, the bus rapid transit system, in Johannesburg and
the City of Cape Towns integrated rapid transit system. Institution
of Civil Engineers (ICE) president Professor Paul Jowitt, speaking
at the recent International Development Conference, in Cape
Town, summarised the role of the engineering profession in economic
growth and social development: engineers should contribute to
resolving the issue of demand for an infrastructure platform
in an increasingly urbanised world, which will help to uplift
a large portion of the worlds growing population from poverty.
But to achieve that aim, there is the requirement not only that
youth are attracted to the profession, but also that the systems
are in place to train, mentor and register engineers. This,
in turn, requires both demand for engineers and respect for
the status of engineers in a society.
The good news, in the local context, is that the demand for
engineers in South Africa is strong and will continue to increase.
In fact, the fundamentals are such that few would probably contradict
the assertion that engineering could well be poised to emerge
as the profession of the next decade, if not the next century.
University of the Witwatersrand (Wits) Dean of the Faculty of
Engineering and the Built Environment Professor Beatrys Lacquet
tells Engineering News that the environment is now such that
engineering graduates find employment with ease, while the appetite
for their skills is so strong that companies seeking to secure
engineering graduates do so through offering attractive bursaries.
This assertion is supported by Professional Assignment Group
(PAG) MD Vicki Marais-Swanepoel, who reports that there has
been steady growth in demand across disciplines. She says that
PAG, a division of comprehensive employment services provider
the Kelly Group, has also noted a significant pick-up in the
demand for engineers in developing countries outside South Africa,
particularly in the rest of Africa and in the Middle East. Marais-Swanepoel
says that clients regard experience as a requirement when looking
for employees and this is a challenge for new graduates. However,
she says that the outlook for graduates is positive and there
are few well-trained qualified engineers coming out of university
who cannot find employment.
Job-Hopping Temptation
She cautions, though, that graduates entering the working environment
should make careful decisions about career moves and should
not change jobs too frequently in pursuit of a higher salary.
Research-based executive search consul- tancy Woodburn Mann
CE Dr Trevor Woodburn says that one of the challenges facing
engineers is the temptation to advance their salaries by changing
jobs too quickly without establishing their skills set. Woodburn
Mann consultant Andrew Woodburn says that this is particularly
relevant for previously disadvantaged graduates owing to South
Africas historically skewed skills set, which has created an
artificial minority of black engineers, whose services are now
highly sought after. His advice, though, is for young engineers
to aim to stay with a company for 24 months to 48 months to
develop a solid skills base for the rest of their careers before
changing jobs. He adds that the company has also noted an increased
demand for engineers from developing regions, such as the Middle
East, Africa, South America and the old Soviet bloc, as this
is where many major engineering projects are under way. Demand
in these regions is particularly focused on engineers that have
experience in megaprojects, senior technical engineering or
project management.
Changing Landscape
But the buoyant employment landscape for engineers in South
Africa has also shifted towards an increased focus on specialised
project component work and contract employment in place of permanent
jobs. Andrew Woodburn says that a number of factors have contributed
to the increase in contract-type employment. Many senior technical
engineers exited the industry when black economic empowerment
requirements were introduced in the engineering sector about
ten years ago. The senior technical engineers were then employed
on a contractual basis in order to retain their skills in industry
without negatively impacting on transformation statistics. He
adds that the rising popularity of contracting has also contributed
to an increase in the number of specialist contracting companies
that have a focused area of work and are contracted to projects
in a specific area of expertise. The growth of these types
of companies shows that there has been an increase in the awarding
of larger specific contracts to organisations. Contracting has
definitely become an art in the engineering environment, he
adds. Marais-Swanepoel believes that South Africa has been relatively
more conservative in its approach to business than the rest
of the world, which has influenced the trend towards contract
employment in engineering. As a result, there is tension between
the project-based nature of the engineering sector and people
wanting the security of permanent employment. It is coming
through in debates about the labour industry, where there is
a drive for people to be permanently and not temporarily employed,
which does not always support flexible business practices,
she adds. There has also been a shift in the remuneration of
engineers over the past ten years as the discrepancies between
the salaries of managerial engineers and those that remain technical
engineers have been significantly reduced. Andrew Woodburn says
that senior technical engineers are better remunerated and have
better career prospects than they did ten years ago.
Futureproof
The growth in demand for engineers is not restricted to current
infrastructure projects, as the long-term development of South
Africa will mean that there is a steady supply of job opportunities
for engineers well beyond the current decade. Lacquet says that
engineers are able to generate growth as they tend towards entre-
preneurial endeavours if work is not readily available. The
more engineers we have, the faster the economy will grow, she
says. The World Competitiveness Yearbooks annual report on
the competitiveness of nations, which ranks countries according
to how their environments create and sustain the competitiveness
of enterprises, says that South Africa improved its 2009 rating
to forty-eighth position. In 2008 and 2007, it was ranked fifty-third
and fiftieth respectively. University of Cape Town (UCT) Dean
of the Faculty of Engineering and the Built Environment Professor
Francis Petersen says that the popularity of particular engineering
disciplines at university is often out of sync with demand.
School leavers are encouraged to study engineering when they
see major projects under way, without considering the lag of
about four years to five years before graduates will be in a
position to enter the workplace. Lacquet says there are, however,
a number of future-focused engineering sectors, where students
are being trained in anticipation of growth in demand for such
disciplines. A notable example is the aerospace industry a
field in which many prospective engineering students are already
interested, but which has received further impetus as a result
of government having identified it as a growth area in which
South Africa has a competitive edge. Other forward-looking programmes
that are increasing in popularity include nuclear engineering
and biomedical engineering. The biomedical engineering programme
at Wits has been running for over five years and each year has
a consistently high number of applications for the course. It
is a future-orientated programme and, as we continue to mature
in engineering in South Africa, I think that this is one of
the areas that we can grow into, says Lacquet. However, while
these newer disciplines are experiencing increased interest
from students, Lacquet says that, at Wits, chemical engineering
remains a consistently popular course. Petersen says that the
two most popular courses at UCT are chemical engineering and
civil engineering, and that chemical engineering also has an
even mix of applications from women and men. University of Pretoria
(UP) Dean of Engineering, Built Environment and Information
Technology Professor Roelf Sandenbergh says there is consistent
interest across the disciplines but that, over time, chemical,
civil, electronic, industrial and mechanical engineering have
remained popular. Sandenbergh adds that the smaller courses
are also fully subscribed and the number of graduates being
produced in mining engineering, in particular, is favourably
comparable with numbers at overseas institutions.
Capacity Constraints
While there is a high demand from industry for engineers and
a significant interest from school leavers in the discipline,
capacity constraints do hinder the increased supply of engineering
graduates into the workplace. Wits reports up to 14 applications
for every place available across its engineering courses, and
UCT and UP also have high numbers of applicants wishing to study
engineering. Sandenbergh says that this year, for the first
time, the university had to turn away students who qualified
for admission to study engineering. He adds that this is evidence
of a significant need for local tertiary institutions to increase
their capacity. UP has a R400-million capacity increase programme
in place and the long-term aim is to double the universitys
facilities, which currently cater for about 5 000 students,
to achieve an internationally competitive capacity figure and
encourage South Africans to study in the country. The initial
construction for the expansion programme is scheduled to be
finished at the beginning of 2011. Sandenbergh hopes this will
eliminate the possibility of having to turn away applicants
who qualify to study engineering. UP enrolment statistics for
the past decade indicate that the number of undergraduates studying
engineering more than doubled between 1999 and 2009. About 1
125 first-year students enrolled at the university in 2009,
compared with about 600 new undergraduates in 2002. This increase
has been distributed evenly across disciplines. Petersen points
out that human-resource planning at tertiary institutions needs
to be revised and effectively implemented; current expansion
planning programmes are not sufficiently comprehensive and do
not always effectively measure the projected growth patterns
for the demand from industry for engineers. Sandenbergh believes
that, in the long term, it would be preferable for tertiary
institutions to produce an excess of engineering graduates to
stimulate entrepreneurship. Lacquet concurs that engineers are
trained to be resourceful and ingenuity is encouraged so that
they are able to start their own businesses and contribute to
economic growth. Marais-Swanepoel says that the need to develop
a broader base of engineers is a significant concern and business
needs to continue to support students through bursaries. Further,
once graduates enter the workplace, they also need to have support
to establish their careers and remain in the engineering industry.
Andrew Woodburn agrees that new graduates need support from
their companies to consolidate their skills when they enter
the workplace. Woodburn Mann has carried out research on the
significant components that companies need to understand to
assist career management. These include effective induction
and performance management. He says that where these two practices
are in place and well managed, employers contribute positively
to the success of employees careers with their company.
School Curriculum
The quality of the maths and science knowledge of matriculants
applying to study engineering at university is another area
of concern but tertiary institutions are working with schools
to improve the quality of teaching in these subjects at school
level. Petersen says that UCT aims to partner with teachers
to improve their knowledge and teaching skills. However, of
the students who qualify to study engineering, the success rate
of first-years who end up completing their degrees is 65% to
70%, which Sandenbergh says is not out of line with international
trends. Nevertheless, the fundamentals are in place: the demand
for engineering skills is robust; interest among secondary school
leavers is stronger than it has been for years; companies are
prepared to invest in engineer development; and there are relatively
good prospects of a strong project pipeline for some years to
come. That said, South Africa will have to deal with some of
the key constraints, from poor maths and science teaching through
to a lack of educational and training capacity and mentorship
to ensure that this new wealth of talent is truly converted
into a national asset.